UPDATE Station Lift Install at Barnt Green Train Station 2025
The lift installation is due to begin on Saturday 25th January 2025. Please see link below that shows a video of the process. The lift towers will be assembled in the car park and there should always be some limited station parking. Access to the ticket machine in the Platform 4 car park will be retained during the work. While part of the platforms are cordoned off, only 4 of the 6 carriage doors will open. Work will take place at night/weekends. The installation should be complete by 31st August 2025.